Sample engagement timelines

There is no standard engagement timeline — history, language access needs, staff capacity, Board calendar, and trust all shape it. This table gives you a floor, not a ceiling.

Updated August 28, 2026 at 1:59 PM PDT

Download PDF

Minimum lead times by level

LevelMin. planning leadActive engagementReport-backMinimum total
Inform2 weeksN/A1 week3 weeks
Consult4 to 6 weeks2 to 3 weeks2 weeks8 to 11 weeks
Involve6 to 8 weeks4 to 6 weeks3 weeks13 to 17 weeks
Collaborate10 to 14 weeks6 to 10 weeks4 weeks20 to 28 weeks
Empower4 to 6 monthsOngoingOngoing6+ months

These are minimum lead times under favorable conditions. Complex projects, hard-to-reach communities, multilingual engagement, and low baseline trust all require more time. Plan accordingly.

What it looks like in practice

A county planning department is redesigning a community park in a neighborhood with a significant Spanish-speaking population and a history of low participation in county processes. Staff spend four weeks in pre-engagement conversations with local CBOs and neighborhood leaders before anything goes public. Three bilingual listening sessions run at different times and locations, with food and childcare provided. A bilingual survey runs concurrently. Input shapes the final design priorities before the project goes to the Board. A bilingual What We Heard summary goes back to participants through the same channels used for outreach within 30 days.