TEST: This is a design test. Data shown has not been fully reviewed and is for test use only.

Trash Capture Devices (Shoreline, Seminary, Goodmans, Blithedale)

About

Category
Water Resources: Drainage
Status in the plan
Ongoing
Total project cost estimate
$5,678,043

Funding

Funding for Trash Capture Devices (Shoreline, Seminary, Goodmans, Blithedale)
Amount
Prior approvals$1,000,000
Proposed FY27$4,678,043
Programmed FY28$0
Programmed FY29$0
Programmed FY30$0
Programmed FY31$0
Total funding in the plan$5,678,043
Additional funds needed$0

Source

Figures are whole dollars as the book prints them. Projects are listed as the book lists them; the book names no department or fund for a project. On a project, funding in the plan is its prior approvals plus the five programmed years; programmed is the five years only. A project's cost estimate is its funding in the plan plus the additional funds still needed.