Marinwood New Traffic Signals: Marinwood/Miller, Miller/Las Gallinas, Mt Lassen/Lucas Valley

About

Category
Transportation: Bike/Ped/Traffic
Status in the plan
New
Total project cost estimate
$1,800,000

Funding

Funding for Marinwood New Traffic Signals: Marinwood/Miller, Miller/Las Gallinas, Mt Lassen/Lucas Valley
Amount
Prior approvals$0
Proposed FY27$50,000
Programmed FY28$250,000
Programmed FY29$1,500,000
Programmed FY30$0
Programmed FY31$0
Total funding in the plan$1,800,000
Additional funds needed$0

Source

Figures are whole dollars as the book prints them. Projects are listed as the book lists them; the book names no department or fund for a project. On a project, funding in the plan is its prior approvals plus the five programmed years; programmed is the five years only. A project's cost estimate is its funding in the plan plus the additional funds still needed.