Airport Fuel Farm Secondary Containment [Near Term]

About

Category
Facilities: County Facilities
Status in the plan
Ongoing
Total project cost estimate
$615,000

Funding

Funding for Airport Fuel Farm Secondary Containment [Near Term]
Amount
Prior approvals$40,000
Proposed FY27$575,000
Programmed FY28$0
Programmed FY29$0
Programmed FY30$0
Programmed FY31$0
Total funding in the plan$615,000
Additional funds needed$0

Source

Figures are whole dollars as the book prints them. Projects are listed as the book lists them; the book names no department or fund for a project. On a project, funding in the plan is its prior approvals plus the five programmed years; programmed is the five years only. A project's cost estimate is its funding in the plan plus the additional funds still needed.