TEST: This is a design test. Data shown has not been fully reviewed and is for test use only.

20 NSP Mechanical + BMS

About

Category
Facilities: County Facilities
Status in the plan
New
Total project cost estimate
$275,000

Funding

Funding for 20 NSP Mechanical + BMS
Amount
Prior approvals$0
Proposed FY27$0
Programmed FY28$75,000
Programmed FY29$200,000
Programmed FY30$0
Programmed FY31$0
Total funding in the plan$275,000
Additional funds needed$0

Source

Figures are whole dollars as the book prints them. Projects are listed as the book lists them; the book names no department or fund for a project. On a project, funding in the plan is its prior approvals plus the five programmed years; programmed is the five years only. A project's cost estimate is its funding in the plan plus the additional funds still needed.